Archis Scaffolding was appointed to provide a complete scaffolding and hoist solution for a multi-storey residential development on Herald Street in Bethnal Green. The site’s location next to an active railway and its restricted ground-level access presented unique logistical and safety challenges that required careful planning and precise execution.
Our Solution:
Our team designed and erected a full scaffolding system across all elevations, incorporating full-height sheeting to protect workers and the public. Due to limited space for material storage and deliveries, cantilevered loading bays were installed at each floor, allowing safe and efficient vertical material handling. Additionally, an Alimak Scando 650 goods and passenger hoist, capable of lifting up to 2 tonnes, was integrated into the scaffold to ensure smooth movement of personnel and materials throughout the project.
Safety & Collaboration:
Working adjacent to a live railway demanded stringent safety measures. Physical barriers were installed, and all operatives were PTS-trained to comply with Network Rail safety standards. Archis Scaffolding maintained continuous coordination with the principal contractor and Network Rail, ensuring compliance with all regulations while keeping the project on schedule.
Project Outcome:
The completed system delivered a safe, robust, and highly efficient access solution, demonstrating Archis Scaffolding’s commitment to technical excellence, flexibility, and site-specific safety. This project highlights our expertise in delivering innovative scaffolding solutions for challenging urban construction sites.
Scope of Work
- Scaffold design and erection for all elevations, including full height sheeting
- Physical barrier installation to prevent rail line access (PTS-trained operatives)
- 6-board-wide heavy-duty protection fan installed to perimeter
- Cantilevered loading bays installed at each floor level due to restricted ground access
- Alimak Scando 650 goods and passenger hoist (2-tonne capacity) installed and tied into structure
- Ongoing coordination with ARJ and Network Rail to meet compliance and safety standards
Details of Project
- Project Name: Herald Street
- Location: Bethnal Green, Londonn
- Requirements: Full scaffold design, erection, and access management adjacent to operational railway line; cantilevered loading bays; public protection measures; hoist installation.
- Status: Completed